PERT Calculator
Calculate PERT expected time, standard deviation, and variance from optimistic, most likely, and pessimistic activity estimates.
Turn three-point estimates into a risk-aware duration for project planning and scheduling.
About PERT estimates
PERT calculation examples
Three-point estimates in any consistent time unit.
| Estimates | PERT result | Use case |
|---|---|---|
| 2 optimistic, 5 likely, 8 pessimistic | Expected 5; SD 1 | A balanced range around the likely duration. |
| 3 optimistic, 6 likely, 15 pessimistic | Expected 7; SD 2 | The long pessimistic tail raises expected time. |
| 10 optimistic, 10 likely, 10 pessimistic | Expected 10; SD 0 | No stated uncertainty produces zero variance. |
How to use the PERT calculator
- Choose one time unit and estimate the fastest realistic completion time.
- Enter the duration most likely under normal working conditions.
- Enter the slowest realistic duration under adverse conditions.
- Click Calculate PERT Estimate and use expected time plus uncertainty in your schedule.
PERT calculator FAQ
Why is the most likely estimate multiplied by four?
Classic PERT uses a weighted average that emphasizes the central scenario. This keeps an extreme endpoint from dominating while preserving information about uncertainty.
Can I enter hours instead of days?
Yes, PERT is independent of the chosen time unit. All three inputs must use the same unit, and the expected time and standard deviation will use it too.
What does PERT variance mean?
Variance is the square of the activity standard deviation and measures spread. It is especially useful because variances of independent activities can be added along a project path.
Must the estimates be in ascending order?
Yes, the optimistic duration should not exceed the most likely duration, which should not exceed the pessimistic duration. Revisit the scenario definitions if that order does not hold.
Does PERT guarantee a completion date?
No, it summarizes assumptions rather than predicting every event. Dependencies, correlated risks, resource limits, and scope changes still require active project management.